Subdivision developer brought a breach of contract action against the contractor who had been engaged nine years previously to pave the roads in the subdivision after the contractor refused to complete the second phase of paving for the roads at the price specified in the contract. The contractor moved for summary judgment on the grounds that the provision in the contract relating to the second phase of paving was a separate offer which had not been accepted by the developer and that the action was barred by laches and the statute of limitations. Developer also moved for summary judgment. The trial court granted summary judgment to developer and denied summary judgment to contractor. Contractor appeals. Discerning no error, we affirm the judgment of the trial court.
Case Number
M2014-02043-COA-R3-CV
Originating Judge
Chancellor Ronald Thurman
Case Name
Avery Place, LLC, et al v. Highways, Inc.